- Client Confidential
- Location Ireland
- Sector Data Centre Projects
- Date March 26, 2021
The aim of this project was to design, manufacture and install bespoke switchgear and busbar into an existing building in North Dublin. Additionally, the project also required a SCADA and Control System which would be installed onto its own independent network.
PROJECT AIM
The aim of this project was to design, manufacture and install bespoke switchgear and busbar into an existing building in North Dublin. Additionally, the project also required a SCADA and Control System which would be installed onto its own independent network.
KEY FACTS
Country: Ireland
Value: £22 million
Industry: Data centre 18MW IT Capacity
Products: MV Modular Plantrooms, LV Switchgear, IBAR, DATABAR, SCADA control monitoring system and Control Panel, Switch Panels
Time frame: 15 months
Year: 2019
PROJECT CHALLENGES
The project required Anord Mardix, and other electrical engineering product manufacturers including Schneider Electric, to create a bespoke critical power solution to a pre-existing building.
A pre-existing building can pose a few challenges, as it requires the products utilised in the project to adapt to the space and building capabilities available to the client.
Anord Mardix and the other manufacturers within the project had to therefore work closely with the general contractor to create bespoke products, which were made to match the the parameters of the project and the needs of the client.
THE ANORD MARDIX SOLUTION
LV Switchgear
5000amp IBAR (4km)
400amp DATABAR (3km)
SCADA control monitoring system
Switch Panels
2 Power Pods; including MV
Switchgear and Control Panels
PROJECT CONCLUSION
Within this project, Anord Mardix also installed fiber and copper network in the buildings, which are used for communication and control purposes.
The project was completed within the agreed upon time frame (15 months) and the client was completely satisfied with the level of engineering expertise and the installation and product quality.
The client has since begun the 2nd phase of this project with Anord Mardix, which, upon completion, will create a 5-building campus totalling just short of 80MW of IT load. This campus will also have a further 8MW planned on a second site just a short distance away.